The drawings have changed. Does the client’s budget still hold?
The client is happy with the revised kitchen plan. Widening the opening to the garden gives them the view they wanted from the kitchen table. As far as they can see, the house is the same size and the only thing that’s got bigger is the set of doors. “How much extra are we talking about?”
It’s a fair question. Before the engineer develops the new opening or the architect spends time detailing the threshold, I’d want to know two things. How much has the change added, and how much room was there in the budget to begin with? The answers can be quite different.
Start with the drawing the client last had costed
When an architect sends me revised drawings, I ask for the cost plan the client last saw and the drawing issue it was based on. The earlier rear elevation might show a three-metre opening, but the estimate might carry a lump sum for glazing across the whole house. I need to establish how much of that sum covered the rear doors. Deduct the whole glazing allowance and we’ve just taken the upstairs windows out of the budget as well.
I also want to know what figure the client actually approved. If it’s the total they have available for the project, we need to set aside fees, VAT and other client costs before we know how much they can spend on the works.
What does the wider opening actually add?

Take a refurbishment where the opening in the existing rear wall increases from three metres to five. The original scheme already needed doors, a beam, temporary support and some making good. All four are in the cost plan. This is how I’d set out the change for the architect.
Work at the rear opening | 3 m opening | 5 m opening | Difference |
|---|---|---|---|
Supply and fit glazed doors | £8,000 | £14,000 | +£6,000 |
Permanent steelwork, bearings and installation | £4,000 | £7,000 | +£3,000 |
Demolition, temporary support and making good | £3,000 | £4,500 | +£1,500 |
Total | £15,000 | £25,500 | +£10,500 |
These are illustrative allowances. Both columns use the same price date and include the contractor’s preliminaries, overheads and profit on the same basis. All figures in this example, including the client’s construction budget, exclude VAT.
The extra £6,000 on the doors is only part of the answer. There’s more wall to take down and a longer span to support. The £10,500 increase allows for a beam bearing on the retained masonry. I’d ask the engineer whether that looks feasible. If posts and new foundations are a realistic possibility, I’d show what that alternative could cost and check how much of it the existing risk allowance covers. That could change the client’s decision.
How much room was there in the budget?
Suppose the client agreed a £500,000 construction budget and the last cost plan came in at £495,000, including the refurbishment contingency. That left £5,000 to spare. With the wider opening, everything else unchanged and the contingency intact, the forecast becomes £505,500.

That gives the architect a conversation worth having. “The wider opening adds about £10,500 on the information we have. We had £5,000 spare, so we’re £5,500 over the budget you agreed. How important is the full width to you?”
The client may happily find the extra money. If the limit is firm, the architect could ask the engineer whether retaining a little more wall would simplify the support, or agree a saving elsewhere with the client. I’d be wary of quietly taking £5,500 from the contingency to make the figures fit. The client gets the wider opening, but there’s now £5,500 less available for whatever turns up when the house is opened up.
On a live job, several things may have moved since the last plan. If the tender date has slipped or a survey has identified repairs to the existing roof, show those amounts separately. Otherwise the architect can end up defending a design change for costs the client would have incurred with either scheme.
I’d finish the meeting by recording which drawing the client wants developed, what construction budget they’ve agreed and what we still need back from the engineer. That gives the design team a clear instruction before anyone spends another afternoon detailing the wrong opening.
Related reading
No drawings yet? Use the calculator with your client to get a starting range for the building work before your first meeting.